Table 1 shows the sequence of activities and their respective duration in a week project. Use it to answer the question that follow.
i) Construct a network diagram to represent the information in Table 1. (3marks)
ii) Identify the critical path from the network diagram. (3marks)
iii) Assuming task D was delayed for 2 weeks, determine the possible finish time for the project.